DISPLAY BOARD NO. 1
(Proforma for Display Board No.1, of Size 6 feet X 4 feet to be provided outside the premises, at the Main Gate of the Unit.)
- Date of Information Update :
- NAME OF THE COMPANY (write in bold) :
- Address :
- Contact Person : Contact Number :
Designation :
5. Total Capacity / Production :
Weeks | Date | Raw materials | Products | Wastes |
Previous week | From : To : | |||
Current week | From : To : |
6. Production Flow Chart indicating points of waste (solid, liquid & gaseous)generation :
7. Consent under Air and Water Act issued on............., valid upto...........
7(a) Conditions for Effluent Discharge:
(i) Quantity of Effluent per day :
Trade EffluentNon- Trade Effluent
(ii) Quality of Treated Effluent (specify the relevant pollutant):
(a) pH: ....... (b) TSS: ...... (c) TDS: ..... (d) BOD: ......
(iii) Mode of Disposal of Treated Effluent :
7(b) Conditions for Air Emissions :
(i) Stack Height(s) (ii) Capacity of DG set
(iii)
Fuel data | DG set | Furnace | Boiler |
Type of fuel | |||
Quantity of fuel | |||
Pollutants |
(iv) Quality of Air Emission (specify the relevant pollutants for the industry):
8. Authorization under Hazardous Waste (Management & Handling) Rules issued on ........, valid upto.......
8(a) Authorisation granted for HW generation under the conditions :
(i) Category of waste generated :
(ii) Quantity of Waste at storage facility :
(iii) Waste disposal facility :
--------------------------------------------------------------------------------------------------
DISPLAY BOARD NO. 2
(Proforma for Display Board No.2, of Size 6 feet X 4 feet to be Provided outside the Premises, at the Main Gate of the Unit.)
1. Effluent Discharge and Treatment
1(a) DAILY monitoring of ETP :
Date | Quantity(KL) | Mode of disposal (drain/sewer/land) | Type & Capacity of ETP | Type of treatment in ETP |
1(b) Results of latest analysis of Effluent Quality :
Prescribed Parameters | ||||||
Prescribed Limits | ||||||
Input to the ETP with Date | ||||||
Output from the ETP with Date |
2. Air Emissions and Control :
Date | Capacity of Boiler/ Furnace (ltrs or Kg per day) | Fuel Consumption (ltrs or Kg per day) | Air Pollution Control System | D.G. sets (KVA) | Stack Height(s) (Mtrs above ground) |
Prescribed Parameters | ||||||
Prescribed Limits | ||||||
Latest Monitoring Results of Air Emission with Date |
3. Hazardous Waste Generation :
Date | Category of Waste | Quantity of Waste | Mode of Storage | Capacity of Remaining Storage | Final Disposal | |
Quantity | Destination | |||||
Hazardous Chemicals | Quantity Used | Safety Measures for Storage & Handling |